Summary
The Board awarded the ARPA-funded Earlimart sewer project to 99 Pipeline for $1.4 million — well below the $2.1 million engineer's estimate — with $83,000 set aside for contingencies.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 5, 2026.
Impact analysis
$1.4 million in federal ARPA funds — roughly $700,000 under the engineer's estimate.
Earlimart residents get upgraded sewer infrastructure funded by federal dollars.