O
Tulare County
← All issues
roadsHigh priorityopen

Mineral King Road & Wishon Drive Permanent Restoration Bid Dispute

Tulare County

Summary

The board split over whether to waive a paperwork error by low bidder Rehak Construction, whose bid was $115,000 below the next bidder. After one failed vote, the contract went to Rehak for $317,001.62, with repairs to be reimbursed at 88% by the federal emergency relief program.

At a glance

Total mentions
6
Last 30 days
0

Discussed at 2 meetings in the last 60 days; most recently Sep 22, 2026.

Impact analysis

💰Financial impact

County road funds cover it, but 88% is expected back through FHWA emergency relief.

✅Who benefits

Travelers between Ponderosa and Johnsondale who need the Western Divide Highway repaired before winter.

⚠️Who could be affected

Greg Bartlett Construction, which protested the bid and lost its challenge.

Mentions & discussions (3)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Tulare County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.